A Guide to the Planning Process

 

Are you concerned about a planning-related issue?



This step by step guide shows you how the process works:

1. Developer Applicant prepares Planning Application. A Permit is required when the application seeks to go beyond
  what is allowed in the Planning Scheme e.g. Removal of significant trees, reduced setback, exceeding permitted
  height, etc.
 
2. Letters are sent to adjoining neighbours and an advertising sign is erected at the front of the site, objectors have 14
  days to object. In reality the time to object is up to when the application is considered by the planning officer.
  Currently there is a backlog so it could be weeks or months after the closing date. Technically if Council doesn’t
  make a decision within 60 days the applicant can go directly to VCAT for a decision.
 
3. Residents can object on the Council form or by letter. Objections should be based on the planning scheme and
  clearly detail your specific concerns, how the proposal may adversely affect you, and any improvements or changes
  you may want to suggest. For a resident to make a later submission to VCAT, they must have been one of the
  objectors to Council.
 
4. Plans and information about the application can be viewed at Council Planning Department or on line - this includes
  architectural plans, arborist reports, landscape plans and a planning report that demonstrates how the application
  responds to the relevant provisions of the Whitehorse Planning Scheme. Other important information – Planning
  Scheme, Planning Scheme Maps, Aerial photos and Council Maps, Zone Character Statement, Tree removal
  documents.
 
5. If there are less than 12 objectors, Council officers will decide on the application. Where 12 or more objections are
  received, Council will arrange a Forum where residents can raise their concerns with the developer and Council
  representatives and hopefully have them addressed.
 
6. After the forum Council planning staff prepare a report with recommendations and the decision is then made at a
  Council meeting. This aspect allows Councillors some say in the process. Residents can also register to speak at a
  Council meeting.
 
7. Councillors may reject the application leaving the applicant the choice of modifying the plans or to take the matter
  to VCAT. If Council support the application residents can take the matter to VCAT. Applications must be lodged
  within 21 days of the notice of decision.
 
8. VCAT fees apply in both cases. For an objector to make a presentation at a VCAT hearing that has been called by
  the developer the fee is $19.50. If a resident takes a case to VCAT that Council have approved the fee starts at
  $819.70 for a single dwelling up to $1902.80 for projects in excess of $50 million. Fees are detailed on the VCAT
  site https://www.vcat.vic.gov.au/steps-to-resolve-your-case/apply-to-start-a-case/fees-at-vcat